Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract and All Necessary Change Orders with Mountain Cascade of Texas, LLC. for the Construction of the Honey Creek Sanitary Sewer Trunk Main Project
Summary
COUNCIL GOAL: Operational Excellence
(2.1: Balance available resources to accommodate the growth and maintenance needs of the city)
MEETING DATE: September 2, 2025
DEPARTMENT: Development Services / Engineering
CONTACT: Tracy Lund, PE, Assistant Director of Engineering
Melvin Machayo, PE, Senior Utility Engineer
RECOMMENDED CITY COUNCIL ACTION:
* Approval of Resolution.
ITEM SUMMARY:
* This Resolution authorizes the City Manager to execute a contract and all necessary change orders with Mountain Cascade of Texas, LLC. for the Honey Creek Sanitary Sewer Trunk Main Project (CIP Project WW1638) for a total contract amount up to a not to exceed amount of $13,000,000.
BACKGROUND INFORMATION:
* This Resolution is related to a previous Agenda Item (24-1924), dated September 3, 2024, regarding an Interlocal Cooperation Agreement between the City of Mckinney and the North Texas Municipal Water District (NTMWD), for Honey Creek Interceptor Improvements.
* Per the Wastewater Master Plan, and the Interlocal Agreement with NTMWD, a new 48-inch to 42-inch sanitary sewer trunk main generally along Honey Creek (from SH 5 to northwest of US 75) is needed to convey projected wastewater flows in the City's Honey Creek Sewer Basin.
* Construction of the master planned wastewater main will support upcoming and future development in the northwest quadrant of the Honey Creek District.
* HDR Engineering Inc. prepared the construction plans and specifications for this project.
*
The City issued a request for proposals (25-15CSP) to solicit responses from qualified contractors for the construction of Honey Creek Sanitary Sewer Trunk Main Project (WW1638).
o Advertised in the McKinney Courier Gazette and Celina Record.
o Posted on M...
Click here for full text