Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract for Construction Manager at Risk (CMAR) Services with Thos. S. Byrne, Inc. dba Byrne Construction Services of Fort Worth, Texas for Preconstruction Services Related to the McKinney Performing Arts Center Renovation Project (FC2504) in McKinney, Texas
Attachments: 1. Resolution, 2. Proposal
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract for Construction Manager at Risk (CMAR) Services with Thos. S. Byrne, Inc. dba Byrne Construction Services of Fort Worth, Texas for Preconstruction Services Related to the McKinney Performing Arts Center Renovation Project (FC2504) in McKinney, Texas
Summary
COUNCIL GOAL: Enhance the Quality of Life in McKinney
(5A: Create Affordable Recreational and Cultural Arts Activities for
All Ages Throughout the City)
MEETING DATE: August 19, 2025
DEPARTMENT: MPAC
Facilities Construction Department
CONTACT: Andrew Jones, Director of Cultural District
Patricia L. Jackson, PE, Facilities Construction Manager
RECOMMENDED CITY COUNCIL ACTION:
* Approval of the Resolution.
ITEM SUMMARY:
* This Resolution authorizes the City Manager to execute a contract for CMAR services with Byrne Construction Services to provide complete preconstruction services related to McKinney Performing Arts Center Renovation Project (Project No. FC2504).
* The selected firm, Byrne Construction Services, submitted a proposal to provide preconstruction services for an amount not to exceed $ 15,000 along with a proposed construction services fee of 2.75% of the cost of construction, for the McKinney Performing Arts Center Renovation Project.
BACKGROUND INFORMATION:
* The City issued a request for qualifications (25-54CMAR) to solicit responses from qualified firms for construction of the Renovation Construction of the McKinney Performing Arts Center on June 13, 2025.
o Advertised in the McKinney Courier Gazette
o Posted on McKinney TV
o 1,341 matching eBid Supplier Notifications which included 67 HUB supplier notifications
* Out of 1,341 supplier notifications, ten (10) statements of qualifications (SOQs) were received on July 3, 2025.
* A committee comprised of staff from MPAC, Public Works, and City Manager's Office reviewed and ranked the SOQs based on the following criteria:
o 40 Points: Fi...