File #: 23-0910    Name: Bid Rejection - Street Rehab Project 24-06CC
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 11/7/2023 Final action: 11/7/2023
Title: Consider/Discuss/Act on a Resolution Authorizing the Formal Rejection of all Bids under Solicitation 24-06CC FY23 Street Rehabilitation
Attachments: 1. Resolution, 2. Location Map

Title

Consider/Discuss/Act on a Resolution Authorizing the Formal Rejection of all Bids under Solicitation 24-06CC FY23 Street Rehabilitation

 

 

Summary

 

COUNCIL GOAL:                     Operational Excellence

(2A: Balance available resources to accommodate the growth and maintenance needs of the city)

 

MEETING DATE:                     November 7, 2023

 

DEPARTMENT:                      Engineering

                     Procurement Services

 

CONTACT:                       Manjeeta Sitaula, Civil Engineer I

                     Blake Sills, CIP Manager

                     Trey Benton, Buyer II

                     

 

RECOMMENDED CITY COUNCIL ACTION:

•                     Approval of Resolution

 

ITEM SUMMARY:

•                     This Resolution authorizes formal rejection of all bids under Solicitation 24-06CC FY23 Street Rehabilitation.

 

BACKGROUND INFORMATION:

•                     The City issued an Invitation to Bid (24-06CC) for the FY23 Street Rehabilitation on October 1, 2023.

o                     Advertised in the McKinney Courier Gazette and Celina Record

o                     Posted on McKinney TV

o                     469 matching eBid supplier notifications which included 17 Historically Underutilized Business (HUB) suppliers.

•                     Out of 469 supplier notifications, one (1) bid was received and opened by Procurement Services on October 19, 2023.

•                     The Engineer’s Opinion of Probable Construction Cost (OPCC) was $3.5 million for Table 1, $2.0 million for Table 2, $4.5 million for Table 3, $2.5 million for Table 4, $260,000 for Table 5 and $320,000 for Table 6 and the bid received exceeded the budgeted amount for this project by $2,215,138.00. The Engineering department has elected to reject all bids.

 