Title
Consider/Discuss/Act on a Resolution Authorizing the Formal Rejection of all Bids under Solicitation 24-06CC FY23 Street Rehabilitation
 
 
Summary
 
COUNCIL GOAL:                     Operational Excellence
(2A: Balance available resources to accommodate the growth and maintenance needs of the city)
 
MEETING DATE:                     November 7, 2023
 
DEPARTMENT:                      Engineering 
                     Procurement Services
 
CONTACT:                       Manjeeta Sitaula, Civil Engineer I
                     Blake Sills, CIP Manager
                     Trey Benton, Buyer II 
                     
 
RECOMMENDED CITY COUNCIL ACTION:
•                     Approval of Resolution
 
ITEM SUMMARY:
•                     This Resolution authorizes formal rejection of all bids under Solicitation 24-06CC FY23 Street Rehabilitation.
 
BACKGROUND INFORMATION:
•                     The City issued an Invitation to Bid (24-06CC) for the FY23 Street Rehabilitation on October 1, 2023. 
o                     Advertised in the McKinney Courier Gazette and Celina Record
o                     Posted on McKinney TV
o                     469 matching eBid supplier notifications which included 17 Historically Underutilized Business (HUB) suppliers. 
•                     Out of 469 supplier notifications, one (1) bid was received and opened by Procurement Services on October 19, 2023. 
•                     The Engineer’s Opinion of Probable Construction Cost (OPCC) was $3.5 million for Table 1, $2.0 million for Table 2, $4.5 million for Table 3, $2.5 million for Table 4, $260,000 for Table 5 and $320,000 for Table 6 and the bid received exceeded the budgeted amount for this project by $2,215,138.00. The Engineering department has elected to reject all bids.
 