File #: 10-386    Name: Resolution
Type: Resolution Status: Approved and Finalized
In control: City Council Regular Meeting
On agenda: 8/23/2010 Final action: 8/23/2010
Title: Consider/Discuss/Act on a Resolution Approving an Airport Participation Agreement with Texas Department of Transportation (TxDOT)
Attachments: 1. Resolution

Title

Consider/Discuss/Act on a Resolution Approving an Airport Participation Agreement with Texas Department of Transportation (TxDOT)

 

 

Summary

 

MEETING DATE:                     August 23, 2010

 

DEPARTMENT:                                           McKinney Airport Development Corporation

 

CONTACT:                                            Ken Wiegand, Executive Director

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

                     Approval of Resolution for an Airport Participation Agreement with Texas Department of Transportation (TxDOT)

 

ITEM SUMMARY: 

                     A resolution is required by TxDOT Aviation to document the City’s administrative and financial support and acceptance of an Airport Layout Plan Update.

 

BACKGROUND INFORMATION: 

                     The Federal Aviation Administration grant assurances and TxDOT Division of Aviation require that Collin County Regional Airport maintain an up-to-date Airport Layout Plan (ALP) on file with them.

                     Council approved an Airport Master Plan Update that included an ALP Update in November 2004 that has been used to justify all construction projects.

                     Since then, all major aspects of that ALP have been completed or are under construction.

                     Working closely with the City’s “M” corporations and alliance, the proposed ALP Update will take a fresh look at airport development using updated forecasts and business aviation activity. 

 

SPECIAL CONSIDERATIONS:                     

                     All future grant offerings depend on an up-to-date ALP.

                     Project duration should not exceed six months.

 

FINANCIAL SUMMARY:

                     TxDOT will pay for 90% of the ALP update.

 

Participants

TxDOT

City

Total

Estimated Cost Shares

$108,000

$12,000

$120,000

 

BOARD OR COMMISSION RECOMMENDATION:

                     MADC recommends approval of the resolution