Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Construction Contract and All Necessary Change Orders with CGC General Contractors Inc., Haltom City, TX for Construction of the Improvements to Grady Littlejohn Softball & Baseball Complex at Towne Lake (PK2448)
Summary
COUNCIL GOAL: Enhance the Quality of Life in McKinney
(5.1: Create affordable recreational and cultural arts activities for all ages throughout the city)
(5.3: Develop sustainable quality of life improvements within the City of McKinney
(5.4: Promote environmental stewardship initiatives.)
(5.5: Enhance connectivity to parks & civic facilities, schools/education centers, libraries, health care providers, commercial corridors, etc.)
MEETING DATE: May 19, 2026
DEPARTMENT: Parks and Recreation
CONTACT: Amy Kinkade, Director of Parks and Recreation
RECOMMENDED ACTION:
* Approval of the Resolution.
ITEM SUMMARY:
* This Resolution authorizes the City Manager to execute a contract and all necessary change orders with CGC General Contractors Inc., of Haltom City, Texas for the construction of the Grady Littlejohn Complex Improvements (PK 2448) for a total contract amount not to exceed $3,700,000.00.
* City staff worked with LJA Engineering Inc. on preparing the construction plans and specifications as needed for project bidding.
* Staff, along with LJA Engineering Inc. support, recommends awarding the construction bid to CGC General Contractors Inc., in an amount of $3,507,526.77 along with a $175,376.34 contingency for a total not to exceed amount of $3,700,000.00.
BACKGROUND INFORMATION:
* This project will consist of a new concession building/restroom building as well as upgrades to the existing dugouts, walkways, and spectator seating. It will also address drainage and concrete repair.
* The City issued a Request for Competitive Sealed Proposals (26-11CSP) to solicit responses from qualified contractors for the Construction of the Grady Littl...