Legislation Details

File #: 12-100    Name: Comegys H & B LPAFA
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 2/21/2012 Final action: 2/21/2012
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Enter into a Local Project Advance Funding Agreement (LPAFA) with the Texas Department of Transportation (TxDOT) to Construct a Hike and Bike Trail Under US 75 at Comegy’s Creek.
Attachments: 1. Resolution, 2. Location Map

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Enter into a Local Project Advance Funding Agreement (LPAFA) with the Texas Department of Transportation (TxDOT) to Construct a Hike and Bike Trail Under US 75 at Comegy’s Creek. 

 

Summary

 

MEETING DATE:                     February 21, 2012

 

DEPARTMENT:                      Development Services/Engineering

 

CONTACT:                       Jack Carr, P.E., Director of Engineering

                     Dan Heischman, Senior Engineer

                     Lemuel P. Randolph, Director of Parks, Recreation and Open

                     Space

 

RECOMMENDED CITY COUNCIL ACTION:                     

•    Approval of the Resolution.

 

ITEM SUMMARY: 

•                     This Resolution authorizes the City Manager to enter into a Local Project Advance Funding Agreement (LPAFA) with the Texas Department of Transportation (TxDOT) for the construction of a hike and bike trail under US 75 at Comegy’s Creek, for an amount not to exceed $300,000.

 

BACKGROUND INFORMATION: 

•                     The Hike and Bike Trails Master Plan shows a hike and bike trail crossing under US 75 at Comegy’s Creek.

•                     The construction of this trail involves drilling piers to support the trail along the edge of the creek.

•                     It will be easier to drill the piers during the period when the bridge is removed during the construction of US 75; therefore, the contractor for the US 75 project has the best opportunity to construct the trail. 

•                     This LPAFA is a commitment of the City of McKinney to pay TxDOT for the additional trail construction work.

 

FINANCIAL SUMMARY: 

•                     The Resolution authorizes LPAFA for an amount not to exceed $300,000.

•                     Funds for this LPAFA are available in the Capital Improvement Program (PK2257) funded by Parkland Dedication funds. 

 