Title: Consider/Discuss/Act on a Request to Grant an Easement to Oncor Electric Delivery Company LLC on the McKinney Community Development Corporation Parking Lot, located between Virginia and Louisiana Streets east of the DART Railway, for the Virginia and Throckmorton Infrastructure Improvements (Municipal Complex) Project
Attachments: 1. Parking Lot Easement Exhibit

Title

Consider/Discuss/Act on a Request to Grant an Easement to Oncor Electric Delivery Company LLC on the McKinney Community Development Corporation Parking Lot, located between Virginia and Louisiana Streets east of the DART Railway, for the Virginia and Throckmorton Infrastructure Improvements (Municipal Complex) Project

 

Summary

 

COUNCIL GOAL:                     Operational Excellence

                     (2B: Balance available resources to accommodate the growth and maintenance needs of the city)

 

MEETING DATE:                     September 26, 2024

 

DEPARTMENT:                     McKinney Community Development Corporation

 

CONTACT:                     Cindy Schneible, President

                     

ITEM SUMMARY:

                     The City of McKinney Engineering Department and Facilities Construction have been coordinating with Oncor to relocate the existing overhead electric lines to be placed underground within the Virginia Street right-of-way between SH 5 and Throckmorton Street.

                     Oncor requires a dedicated easement outside of the street right-of-way to place an electrical switchgear and associated facilities to provide underground power to the McKinney Municipal Complex and other City owned property east of the railroad.

                     The removal of three parking spaces will be required.

 

BACKGROUND INFORMATION:

                     Construction of the Virginia and Throckmorton Infrastructure Improvements (Municipal Complex) Project (ST2235, WA2235, WW2235) is underway and is expected to be completed by Spring 2025.

                     Oncor, in coordination with Engineering staff, evaluated multiple potential locations for the switchgear. Other locations were not recommended due to environmental concerns, franchise utility conflicts, and potential impacts to City utilities.

 