File #: 20-0775    Name: Soccer Complex Connector Road
Type: Agenda Item Status: Agenda Ready
In control: Parks, Recreation, and Open Space Advisory Board
On agenda: 9/10/2020 Final action:
Title: Consider/Discuss/Act on a Recommendation to City Council for a Resolution Authorizing the City Manager to Execute a Contract with North Rock Construction, LLC of Denton, Texas, for the Construction of the McKinney Soccer Complex at Craig Ranch Connector Road Project

Title

Consider/Discuss/Act on a Recommendation to City Council for a Resolution Authorizing the City Manager to Execute a Contract with North Rock Construction, LLC of Denton, Texas, for the Construction of the McKinney Soccer Complex at Craig Ranch Connector Road Project

 

Summary

 

COUNCIL GOAL:   Enhance the Quality of Life in McKinney                                                               

(5A: Create affordable recreational and cultural arts activities for all ages throughout the city)

(5C: Continue to market and highlight McKinney as a unique destination for residents and visitors alike)

(5E: Develop sustainable quality of life improvements within the City of McKinney)

 

MEETING DATE:    September 10, 2020

 

DEPARTMENT:                      Parks and Recreation

 

CONTACT:                       Michael Kowski, Director of Parks and Recreation

 

 

RECOMMENDED ACTION:                     

•                     Approve the recommendation to City Council.

 

ITEM SUMMARY: 

•                     This park road will provide a connection between two existing parking lots that are to the south and east of the championship field and will greatly improve vehicular flow throughout the complex.

•                     City staff worked with DCBA on preparing the construction plans and specifications as needed for project bidding.

 

•                     Staff recommends awarding the construction bid to North Rock Construction, LLC in an amount of $197,633.03

 

BACKGROUND INFORMATION: 

•                     A total of 8 bids were received.

 

•                     North Rock Construction, LLC submitted the lowest bid for the construction.

 

•                     North Rock Construction has completed projects for the City of McKinney in the past, including Dr. Mack Hill Park and various trail projects.

             

•                     If approved, construction should begin in this fall with a 60 day contract schedule.

 

FINANCIAL SUMMARY: 

•                     This project (PK1906) is a FY19-20 Capital Improvements Program funded by MCDC funds and Parkland Dedication Funds Zone 3. 

 