Skip to main content
File #: 10-339    Name: US 380 Water Main - West Construction
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 7/20/2010 Final action: 7/20/2010
Title: Consider/Discuss/Act on a Resolution Authorizing a Contract for the Construction of the US 380 Water Main - 920 Pressure Plane Connection - West Project.
Attachments: 1. Resolution, 2. Location Map

Title

Consider/Discuss/Act on a Resolution Authorizing a Contract for the Construction of the US 380 Water Main - 920 Pressure Plane Connection - West Project.

 

Summary

 

MEETING DATE:                     July 20, 2010

 

DEPARTMENT:                                           Development Services/Engineering

 

CONTACT:                                            Paul Tucker, PE, Senior Utility Engineer

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

                     Approval of Resolution.

 

ITEM SUMMARY: 

                     This Resolution authorizes the City Manager to execute a construction contract with TNT Pipeline Corporation for the construction of the US 380 Water Main - 920 Pressure Plane Connection - West Project.

                                          Ten bids were received for this project on July 1, 2010.

                     TNT Pipeline Corporation submitted the low bid in the amount of $2,164,391.

 

BACKGROUND INFORMATION: 

                                          This project is an integral component to provide additional capacity out of the University Pump Station for the 920 Pressure Plane.

                     Birkhoff, Hendricks & Carter, L.L.P. is the design consultant for this project.

 

FINANCIAL SUMMARY: 

                     The Resolution authorizes a contract with TNT Pipeline Corporation for an amount not to exceed $2,490,000.

  • Funds are available in the Capital Improvements Program in project WA6011.

 

BOARD OR COMMISSION RECOMMENDATION:

                     N/A