Consider/Discuss/Act on a Resolution Authorizing a Contract for the Construction of the US 380 Water Main - 920 Pressure Plane Connection - West Project.
Summary
MEETING DATE: July 20, 2010
DEPARTMENT: Development Services/Engineering
CONTACT: Paul Tucker, PE, Senior Utility Engineer
RECOMMENDED CITY COUNCIL ACTION:
• Approval of Resolution.
ITEM SUMMARY:
• This Resolution authorizes the City Manager to execute a construction contract with TNT Pipeline Corporation for the construction of the US 380 Water Main - 920 Pressure Plane Connection - West Project.
• Ten bids were received for this project on July 1, 2010.
• TNT Pipeline Corporation submitted the low bid in the amount of $2,164,391.
BACKGROUND INFORMATION:
• This project is an integral component to provide additional capacity out of the University Pump Station for the 920 Pressure Plane.
• Birkhoff, Hendricks & Carter, L.L.P. is the design consultant for this project.
FINANCIAL SUMMARY:
• The Resolution authorizes a contract with TNT Pipeline Corporation for an amount not to exceed $2,490,000.
- Funds are available in the Capital Improvements Program in project WA6011.
BOARD OR COMMISSION RECOMMENDATION:
• N/A