Title
Consider/Discuss/Act on a Resolution Authorizing a Contract for the Construction of the US 380 Water Main - 850 Pressure Plane Connection - East Project.
Summary
MEETING DATE: July 20, 2010
DEPARTMENT: Development Services/Engineering
CONTACT: Paul Tucker, PE, Senior Utility Engineer
RECOMMENDED CITY COUNCIL ACTION:
· Approval of Resolution.
ITEM SUMMARY:
· This Resolution authorizes the City Manager to execute a contract with Wright Construction Company, Inc. for the construction of the US 380 Water Main - 850 Pressure Plane Connection - East Project.
· Eleven bids were received for this project on July 8, 2010.
· Wright Construction Company, Inc. submitted the low bid in the amount of $3,997,983.00.
BACKGROUND INFORMATION:
· This project provides an integral element necessary to provide additional capacity for the 850 Pressure Plane at the University Pump Station.
· Birkhoff, Hendricks & Carter, L.L.P. is the design consultant for this project.
FINANCIAL SUMMARY:
· The Resolution authorizes a contract with Wright Construction Company, Inc. for an amount not to exceed $4,398,000.
- Funds are available in the Capital Improvements Program in project WA1006.
BOARD OR COMMISSION RECOMMENDATION:
· N/A