File #: 23-0760    Name: FI2111 FDHQ - Pogue - GMP
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 9/19/2023 Final action: 9/19/2023
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract for Construction Manager at Risk (CMAR) Services with Pogue Construction Company, LP of McKinney, Texas for a Guaranteed Maximum Price (GMP) for Construction Services Related to the Design and Construction of the McKinney Fire Department Headquarters Project Located at 2100 Taylor Burk Drive, McKinney, Texas
Attachments: 1. Resolution, 2. GMP Proposal
Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract for Construction Manager at Risk (CMAR) Services with Pogue Construction Company, LP of McKinney, Texas for a Guaranteed Maximum Price (GMP) for Construction Services Related to the Design and Construction of the McKinney Fire Department Headquarters Project Located at 2100 Taylor Burk Drive, McKinney, Texas
SUMMARY

COUNCIL GOAL: Safe & Secure Community
(6A: Maintain Meaningful Public Safety Performance Measures)
MEETING DATE: September 19, 2023
DEPARTMENT: Fire Department
Public Works
CONTACT: Paul Dow - Fire Chief
Patricia L. Jackson, PE, Facilities Construction Manager

RECOMMENDED CITY COUNCIL ACTION:
* Approval of the Resolution.
ITEM SUMMARY:
* This Resolution authorizes the City Manager to execute a Construction Manager at Risk contract with Pogue Construction Company, LP, for the design and construction of the Fire Department Headquarters Project (FI2111) located at 2100 Taylor Burk Drive, McKinney, Texas 75071.
* The selected firm, Pogue Construction Company, LP, submitted a Guaranteed Maximum Price proposal to provide construction manager at risk services for a GMP amount of $47,863,091, including the previously agreed upon construction services fee of 2.0% of the cost of construction, for the Fire Department Headquarters Project.
BACKGROUND INFORMATION:
* The construction documents were issued on August 3, 2023 and were advertised for bids by Pogue Construction Company, LP.
* Pogue compiled the bids, verified the scopes of work with each proposed subcontractor and submitted a final Guaranteed Maximum Price for approval.
* With this approval, Pogue will be notified to begin construction with completion scheduled for August, 2025.
* Pogue Construction Company, LP has successfully completed multiple City of McKinney projects, including the original Public Safety Building, the Public Safety Support Building and various renovations of the Public Safety ...

Click here for full text