Legislation Details

File #: 11-238    Name: US 75 Utility Relocation - South SUA
Type: Resolution Status: Approved and Finalized
In control: City Council Regular Meeting
On agenda: 5/17/2011 Final action: 5/17/2011
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Standard Utility Agreement with TxDOT for Reimbursement of Expenses for the US 75 Water and Sanitary Sewer Relocation Project from SH 121 to White Avenue - Phases I and II.
Attachments: 1. Resolution, 2. Location Map

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Standard Utility Agreement with TxDOT for Reimbursement of Expenses for the US 75 Water and Sanitary Sewer Relocation Project from SH 121 to White Avenue - Phases I and II.

 

Summary

 

MEETING DATE:                     May 17, 2011

 

DEPARTMENT:                     Development Services/Engineering

 

CONTACT:                     Danny Still, PE, CIP Engineer

                     Paul Tucker, PE, Senior Utility Engineer

 

 

RECOMMENDED CITY COUNCIL ACTION:

•                     Approval of Resolution.

 

ITEM SUMMARY:

•                     This Resolution authorizes the City Manager to execute a Standard Utility Agreement with TxDOT for reimbursement of expenses for the US 75 Water and Sanitary Sewer Relocation Project from SH 121 to White Avenue - Phases I   and II.

 

BACKGROUND INFORMATION:

•                     TxDOT has completed the design of the widening of US 75 from SH 121 to White Avenue and has awarded the project to a contractor.

•                     TxDOT construction is scheduled to begin no later than December 1, 2011.

•                     The relocation of the water and sewer mains is needed to address conflicts with the proposed pavement.

•                     This Standard Utility Agreement will establish the reimbursement percentage that the City will receive from TxDOT for the cost of the relocations.

•                     The utility relocation construction plans have been completed and easement acquisition is underway.

•                     This agreement must be fully executed before City relocation work begins in order for the City relocation work to be eligible for reimbursement from TxDOT.

 

FINANCIAL SUMMARY:

•                     The total cost of the City utility relocation project, including design, construction, easement acquisition, project management, and construction inspection is estimated to be $4,500,000.

•                     The estimated reimbursement percentage from TxDOT will be 56% ($2,520,000) and will be paid in 2012, after the completion of the utility relocation project.

 

BOARD OR COMMISSION RECOMMENDATION:

•                     N/A