File #: 17-933    Name: Redbud Pump Station 794 PP
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 9/19/2017 Final action: 9/19/2017
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract and All Necessary Change Orders with S.J. Louis Construction of Texas, Ltd. for the Construction of the Redbud Pump Station 794 PP Transmission Water Line
Attachments: 1. Resolution, 2. Letter of Recommendation, 3. Bid Tabulations, 4. Location Map
Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract and All Necessary Change Orders with S.J. Louis Construction of Texas, Ltd. for the Construction of the Redbud Pump Station 794 PP Transmission Water Line

Summary

COUNCIL GOAL: Direction for Strategic Growth

MEETING DATE: September 19, 2017

DEPARTMENT: Development Services / Engineering

CONTACT: Nick Ataie, PE, Interim CIP Manager
Blake Sills, PE, CIP Engineer

RECOMMENDED CITY COUNCIL ACTION:
* Approval of Resolution.

ITEM SUMMARY:
* This Resolution authorizes the City Manager to execute a contract and all necessary change orders with S.J. Louis Construction of Texas, Ltd. for the construction of the Redbud Pump Station 794 PP Transmission Water Line for a total contract amount not to exceed $3,400,000.

BACKGROUND INFORMATION:
* Lockwood, Andrews & Newman, Inc. prepared the construction plans for this project.
* ?n Thursday, August 31, 2017 the Purchasing Department opened bids for the project and three (3) bids were received. The following is a summary of the bids:
Bid No.
Bidder
Bid Amount|1010|S.J. Louis Construction of Texas, Ltd.
$3,082,258.00|1010|Flow-Line Construction, Inc.
$3,717,395.00|1010|BAR Constructors, Inc.
$3,853,660.00
* S.J. Louis Construction of Texas, Ltd. submitted the low bid in the amount of $3,082,258.00.
* S.J. Louis Construction of Texas, Ltd. submitted references and qualifications that were verified in accordance with the bid specifications as shown in the attached letter of recommendation.
* The contract documents require that this project be substantially completed within 240 calendar days after issuance of the Notice to Proceed, which is expected October 2, 2017. Construction is expected to be substantially complete by June 2018.
* The contract documents contain a Milestone date of December 21, 2017, for the construction of the transmission line to be complete on the Collin College Public Safety Training Facility (PSTF) site.
...