File #: 17-1114    Name: Country Lane Extension - Design Contract
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 11/7/2017 Final action: 11/7/2017
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Garver, LLC for Professional Engineering Design Services for the Country Lane Extension Project (ST4372) and Any Necessary Supplemental Agreements
Attachments: 1. Resolution, 2. Location Map

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Garver, LLC for Professional Engineering Design Services for the Country Lane Extension Project (ST4372) and Any Necessary Supplemental Agreements

 

Summary

 

COUNCIL GOAL:                     Direction for Strategic and Economic Growth

 

MEETING DATE:                     November 7, 2017

 

DEPARTMENT:                     Development Services / Engineering

 

CONTACT:                     Nick Ataie, P.E., CIP Manager

                     Blake Sills, P.E., CIP Engineer

 

 

RECOMMENDED CITY COUNCIL ACTION:

                     Approval of Resolution.

 

ITEM SUMMARY:

                     This Resolution authorizes a contract with Garver, LLC to provide consulting professional engineering services for the design of the Country Lane Extension Project (ST4372) for an amount not to exceed $180,000.

 

BACKGROUND INFORMATION:

                     Upon completion of the ongoing TxDOT FM 546 construction project, a connection is proposed from the Country Lane and FM 546 intersection to the existing concrete pavement on Country Lane.

                     The project will construct two northbound through lanes, two southbound through lanes, and southbound right and left turn lanes at FM 546.

                     The design will also include improvements to the intersections of Country Lane and existing FM 546, and Airport Road and Industrial Boulevard. A southbound right turn lane will be included in the design of Airport Road and Industrial Boulevard.

                     Garver, LLC submitted a response to RFQ 15-38 for Roadway Design.  They were one of ten firms shortlisted by City Council on October 20, 2015.

                     Garver, LLC submitted a proposal for this project in the amount of $162,770.00.

                     The preliminary opinion of probable construction cost is $1,063,540.

                     The fee for basic services is $84,908.00 (8.0% of the construction cost) and the fee for special services is $77,862.00 (7.3% of the construction cost).

                     Design of this project is anticipated to take six (6) months.

                     Construction is anticipated to take six (6) months to complete.  Construction is anticipated to begin as soon as June 2018 and to be completed by December 2018.

 

FINANCIAL SUMMARY:

                     This Resolution authorizes a design contract and any necessary supplemental agreements with Garver, LLC, for an amount not to exceed $180,000.                     

                     With the approval of this item, $1,320,000 will remain in project ST4372.

 

BOARD OR COMMISSION RECOMMENDATION:

                     N/A