File #: 20-0857    Name: Prestwyck Construction Contract
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 10/6/2020 Final action: 10/6/2020
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with North Rock Construction, LLC of Denton, Texas, for the Construction of a 10 Acre Neighborhood Park Located within the Prestwyck Subdivision
Attachments: 1. Resolution, 2. Award Recommendation, 3. Bid Tabulation
Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with North Rock Construction, LLC of Denton, Texas, for the Construction of a 10 Acre Neighborhood Park Located within the Prestwyck Subdivision

Summary

COUNCIL GOAL: Enhance the Quality of Life in McKinney
(5A: Create affordable recreational and cultural arts activities for all ages throughout the city)
(5C: Continue to market and highlight McKinney as a unique destination for residents and visitors alike)
(5E: Develop sustainable quality of life improvements within the City of McKinney)

MEETING DATE: October 6, 2020

DEPARTMENT: Parks and Recreation

CONTACT: Michael Kowski, Director of Parks and Recreation


RECOMMENDED ACTION:
* Approval of the Resolution

ITEM SUMMARY:
* The 10 acre neighborhood park will include play equipment, splash pad, pavilion, sport-court, shade structures, off street parking, learning stations, fitness stations, pedestrian connectivity and landscaping.
* City staff worked with DCBA on preparing the construction plans and specifications as needed for project bidding.

* The project includes a base bid and 8 alternates:

o Alternate 1: Playground shade structure

o Alternate 2: Playground shade structure

o Alternate 3: Playground swing shade structure

o Alternate 4: Concrete ping pong table

o Alternate 5: Solid Sod Bermuda grass

o Alternate 6: Color concrete at exercise station

o Alternate 7: Sawcut and sandblasted giant chess board

o Alternate 8: Concrete art wall, decomposed granite and mow strip


* Staff, along with DCBA support, recommends awarding the construction bid to North Rock Construction, LLC in an amount of $2,633,249.81 (includes base bid + All Alternates) along with a $75,000 contingency for a total not to exceed amount of $2,708,249.81.

BACKGROUND INFORMATION:
* A total of seven (7) bids were received for this project on August 27, 2020.

* MSB Constructors, Inc, the apparent low bidder, was d...

Click here for full text