File #: 23-015DA    Name: Cocktail Creamery TIRZ No. 1
Type: Resolution Status: Approved
In control: Reinvestment Zone Number One
On agenda: 6/6/2023 Final action: 6/6/2023
Title: Conduct a Public Hearing to Consider/Discuss/Act on a Resolution Approving a Chapter 380 Economic Development Agreement and Project Plan Implementation Agreement with Cocktail Creamery, LLC for a Critical Maintenance Project at 205 East Virginia Street
Attachments: 1. Letter of Intent, 2. Form 1295, 3. Proposed Resolution, 4. Proposed TIRZ Agreement, 5. TIRZ Funding Summary, 6. Presentation

Title

Conduct a Public Hearing to Consider/Discuss/Act on a Resolution Approving a Chapter 380 Economic Development Agreement and Project Plan Implementation Agreement with Cocktail Creamery, LLC for a Critical Maintenance Project at 205 East Virginia Street

 

Summary

 

COUNCIL GOAL:                     Enhance the Quality of Life in McKinney by promoting reinvestment activities and ordinance changes in Historic Downtown McKinney that balance preservation of historic character and current market needs.

 

MEETING DATE:                     June 6, 2023

 

DEPARTMENT:                      Development Services - Planning Department

 

CONTACT:                       Paula Jarrett Nasta, AIA, Planning Manager

                     Jennifer Arnold, AICP, Director of Planning

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

                     Staff recommends approval of the Chapter 380 Economic Development agreement and Project Plan Implementation Agreement.

 

ITEM SUMMARY: 

                     The applicant is requesting an economic development grant from Reinvestment Zone Number One in support of the rehabilitation at 205 East Virginia Street (Cocktail Creamery). The request is to assist specifically with the following TIRZ 1 eligible activities under the Vacant/Underutilized Sites/Buildings category of the TIRZ No. 1 Project Plan:

 

                     Critical Maintenance

o                     Plumbing replacement and upgrades

 

                     The total cost for the rehabilitation at 205 East Virginia Street is estimated to be $100,000. The applicant requests a grant from Reinvestment Zone Number One in the amount of $10,462.50 to support plumbing upgrades and replacements.

 

BACKGROUND INFORMATION: 

                     Under Chapter 311 of the Texas Tax Code and Chapter 380 of the Texas Local Government Code, the TIRZ Board has the authority to make loans or grants of TIRZ funds for the purpose of promoting local economic development and stimulating businesses and commercial activity within the reinvestment zone.

 

                     The proposed project(s) is an eligible project in the TIRZ No. 1 Project Plan under the category of Vacant/Underutilized Sites/Buildings, which is defined as “relatively smaller projects (under $5.0 million) for the incremental redevelopment of vacant/underutilized Town Center sites or buildings.”  Specific activities eligible for TIRZ No. 1 funding under the Vacant/Underutilized Sites/Buildings category include:

                                          Environmental Remediation and associated Interior/Exterior Demolition

                     Historic Façade Restoration Improvements/Easements

                     Acquisition and Restoration of Historic Sites (public projects)

                     Street, Utility, and Streetscape Improvements

                     Municipal Land Acquisition

                     Critical Maintenance

                     Fire Suppression

 

FINANCIAL SUMMARY: 

                     The FY22-23 annual budget for TIRZ No. 1 includes funding for Vacant/Underutilized Sites/Building.

o                     The current available funds in this account for FY23 are $300,040.

 

                     Reimbursement and/or grant requests are funded on a first-come, first-serve basis until the maximum fiscal year allotment has been reached. To date for FY23, two 50/50 matching reimbursement or grant requests have been approved

 

                     A full summary of projects that have received TIRZ No. 1 Category II funding is attached to this staff report for your reference.