Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute an Agreement with Griffin/Swinerton, LLC for McKinney National Airport Project AI2353, Hangar/Corp 10 and Customs Facility Subject to the City Attorney’s Approval of the Final Documents.
Summary
COUNCIL GOAL: Maximize the Development Potential of McKinney National Airport
• 3A: Implement initiatives and strategies, including public-private partnerships, to attract and expand corporate and commercial aviation including the viability of passenger service.
• 3B: Identify and implement land use regulations and policies that preserve and expand long-term operational excellence.
MEETING DATE: December 19, 2023
DEPARTMENT: Airport
CONTACT: Ken Carley, Airport Director
RECOMMENDED CITY COUNCIL ACTION:
• Approve Resolution
ITEM SUMMARY:
• The Resolution authorizes the City Manager to execute an agreement with Griffin/Swinerton, LLC for McKinney National Airport Project AI2353, Hangar/Corp 10 and Customs Facility subject to the City Attorney’s approval of the final documents.
BACKGROUND INFORMATION:
• The proposed scope of work for will consist primarily of:
o The construction of the Corp 10 hangar
o The construction of U.S Border Patrol and Customs building
• The construction of the Corp 10 hangar will allow for additional hangar lease and fuel revenue.
• The construction of the U.S. Border Patrol and Customs building (Customs Facility) is required to continue providing U.S. Customs Services to international operators.
• The City Council approved the issuance of certificates of obligation for airport projects at the November 7th meeting. Subsequently the bonds were sold on November 14th and funded on December 7th.
FINANCIAL SUMMARY:
• Griffin/Swinerton, LLC has provided a Guaranteed Maximum Price (GMP) of $22,990,954. The City of McKinney will be responsible for 100% of the GMP.
• Funding for this project is appropriated in the Capital Improvement Program Project AI2353, Hangar/Corp 10 and Customs Facility.
• A budget amendment to fund project AI2353, Hangar/Corp 10 and Customs Facility, is presented as a companion item on this agenda.
• Upon approval of both items, $1,009,046 will remain in project AI2353.
BOARD OR COMMISSION RECOMMENDATION:
• N/A