Consider/Discuss/Act on a Resolution Authorizing the Interim City Manager to Execute a Contract with Halff Associates for Professional Services for Design of a Streetscape Plan
Summary
COUNCIL GOAL: Direction for Strategic and Economic Growth
MEETING DATE: May 3, 2016
DEPARTMENT: Parks, Recreation, and Open Space
CONTACT: Rhoda Savage, Director of PROS
Jenny Baker, Senior Park Planner
RECOMMENDED CITY COUNCIL ACTION:
* Approval of the Resolution as proposed.
ITEM SUMMARY:
* This Resolution authorizes the Interim City Manager to execute a professional services contract with Halff Associates for a Streetscape Plan in an amount not to exceed $30,000.
* Halff Associates is also preparing the update to the Parks, Recreation, Trails & Open Space Master Plan, of which this Streetscape Plan will be a component.
* It will also support the One Community One Vision McKinney 2040 Comprehensive Plan update and associated Thoroughfare Plan.
* The major components of the Streetscape Plan are:
1. Gateway and Entry Monuments
2. Streetscape Colors, Materials and Furnishings
3. Streetscape Design and Development Standards
4. Inclusion into the Parks, Recreation, Trails & Open Space Master Plan
* More specifically, this Plan will provide a unified design theme for the overall roadway system that speaks to materials, colors, use of the city logo and site furnishings (lighting, benches, trash receptacles, signage, etc.). It will also establish standards for design of medians, rights of ways and intersection treatments.
* The Streetscape Plan will be completed at the same time as the Parks, Recreation, Trails & Open Space Master Plan, which should occur around December 2016.
BACKGROUND INFORMATION:
* The need for this plan has arisen from the planning for future growth and imminent development of sections of the City's Thoroughfare Plan in the northwest sector of the City.
* When planning for the design of the ...