File #: 16-1204    Name: Resolution for GMP for Pogue for MPSSB
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 12/6/2016 Final action: 12/6/2016
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract Amendment to the Construction Manager at Risk (CMAR) Services Contract with Pogue Construction Company, LP of McKinney, Texas for a Guaranteed Maximum Price (GMP) Related to the Construction of the Public Safety Support Building Located at 2750 Community Avenue, McKinney, TX 75071
Attachments: 1. Resolution, 2. GMP Proposal
Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract Amendment to the Construction Manager at Risk (CMAR) Services Contract with Pogue Construction Company, LP of McKinney, Texas for a Guaranteed Maximum Price (GMP) Related to the Construction of the Public Safety Support Building Located at 2750 Community Avenue, McKinney, TX 75071

SUMMARY

COUNCIL GOAL: Safe and Secure Community

MEETING DATE: December 6, 2016

DEPARTMENTS: McKinney Police Department
McKinney Fire Department
Public Works, Facilities Construction Division

CONTACTS: Greg Conley, Police Chief
Danny Kistner, Fire Chief
Patricia L. Jackson, PE, Facilities Construction Manager



RECOMMENDED CITY COUNCIL ACTION:
* Approval of the Resolution.

ITEM SUMMARY:
* This Resolution:
* Establishes a Guaranteed Maximum Price (GMP) of $7,120,903 as proposed by Pogue Construction Company, LP which includes $6,978,167 for the base project plus $142,736 for the paving alternative #2 option.
* Authorizes the City Manager to execute a contract amendment with Pogue Construction Company, LP, the Construction Manager at Risk for the McKinney Public Safety Support Building, located at 2750 Community Avenue, McKinney, TX 75071.

BACKGROUND INFORMATION:
* On March 15, 2016 a professional services contract was authorized for Pogue Construction Company, LP to provide Construction Manager at Risk services related to the preconstruction phase of McKinney Public Safety Support Building located at 2750 Community Avenue, McKinney, TX 75071.
* Pogue Construction Company, LP has compiled the bids and submitted a final Guaranteed Maximum Price for consideration and approval by the City Council.
* The original contract allowed for the GMP to be proposed after the completion of the design plans and bidding process.
* The construction documents were issued in September, 2016 and have been advertised for bids by Pogue Construction Company, LP.
* Upon approval, Pogue Constr...

Click here for full text