File #: 18-491    Name: DR5093 Lake 4 TSSWCB Grant - Federal Funds Amendment 1
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 6/5/2018 Final action: 6/5/2018
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Amend the Project Agreement with the Texas State Soil and Water Conservation Board for Federal Funding for the NRCS Lake 4 Dam Rehabilitation Project
Attachments: 1. Resolution, 2. Location Map, 3. Proposed Amendment 1, 4. Signed Agreement
Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Amend the Project Agreement with the Texas State Soil and Water Conservation Board for Federal Funding for the NRCS Lake 4 Dam Rehabilitation Project


Summary

COUNCIL GOAL: Operational Excellence
(2B: Balance Available Resources to Accommodate the Growth and Maintenance Needs of the City)

MEETING DATE: June 5, 2018

DEPARTMENT: Development Services / Engineering

CONTACT: Danny Still, PE, CFM, Drainage Engineer
Kyle Odom, CFM, Environmental Engineering Manager


RECOMMENDED CITY COUNCIL ACTION:
* Approval of the resolution.

ITEM SUMMARY:
* This resolution authorizes the City Manager to amend the Texas State Soil and Water Conservation Board (TSSWCB) Project Agreement for federal funding to increase the maximum agreement amount from $351,000 to $4,500,000.
* The primary reason for the change is to add construction funding to the agreement, which has been the intention all along.
* This amendment also extends the term of the agreement from June 30, 2018, to June 30, 2020, to cover the entire anticipated construction period.

BACKGROUND INFORMATION:
* This dam, known locally as Brinkmann Ranch Lake, is located north of US 380 between Lake Forest Drive and Hardin Boulevard. It does not meet current safety standards. A failure of the dam would result in significant property damage and the potential loss of life.
* City Council approved the original TSSWCB Project Agreement for federal funding at a meeting on January 3, 2017.

FINANCIAL SUMMARY:
* At the time of the original agreement, it was agreed to show $0 for the estimated construction cost then amend the agreement later when actual construction costs were known. The bid opening occurred on May 10, 2018. The low bid amount was $4,960,863.70. The agreement is now being amended to add construction funding.
* The estimated project costs are as follows:
Construction: $ 5,500,000
Land Rights Acquisition: $ 210,000
Contract Admini...