Legislation Details

File #: 22-0398    Name: Amend Chapter 380 - 119 W Louisiana
Type: Resolution Status: Approved
In control: Reinvestment Zone Number One
On agenda: 5/3/2022 Final action: 5/3/2022
Title: Conduct a Public Hearing to Consider/Discuss/Act on a Second Amendment to the Chapter 380 Economic Development Agreement and Project Plan Implementation Agreement with McKinney Knittery/Downtown Dry Goods for the Fa?ade Improvement Project at 119 W. Louisiana
Attachments: 1. Agreement, 2. Agreement (1st Extension), 3. Second Extension Request, 4. Agreement (2nd Extension), 5. Resolution, 6. Presentation

Title

Conduct a Public Hearing to Consider/Discuss/Act on a Second Amendment to the Chapter 380 Economic Development Agreement and Project Plan Implementation Agreement with McKinney Knittery/Downtown Dry Goods for the Façade Improvement Project at 119 W. Louisiana

 

Summary

 

COUNCIL GOAL:                     Enhance the Quality of Life in McKinney

 

MEETING DATE:                     May 3, 2022

 

DEPARTMENT:                      Development Services - Planning Department

 

CONTACT:                       Paula Jarrett Nasta, AIA, Planning Manager

 

ITEM SUMMARY:

 

•                     The proposed amendment to the Chapter 380 Economic Agreement with the McKinney Knittery/Downtown Dry Goods is to further extend the deadline of the obligation to complete the façade improvements until September 30, 2022 (from March 31, 2022).

 

•                     Under the agreement approved by the TIRZ #1 Board on December 1, 2020, McKinney Knittery/Downtown Dry Goods was to:

 

o                     Make façade improvements consisting of storefront restoration.

o                     Receive a “green tag” inspection for the improvements by September 30, 2020.

 

•                     Under this proposed second amendment, the specific obligations of McKinney Knittery/Downtown Dry Goods to construct façade improvements are amended as follows:

 

o                     McKinney Knittery/Downtown Dry Goods shall fund and complete the project on or before September 30, 2022 and shall receive a final “green tag” inspection for the Project at the historic building located at 117 W. Louisiana Street on or before that date. 

 

•                     Except as specifically amended above, all terms and provisions of the original agreement will remain in full force and effect.

 

BACKGROUND INFORMATION: 

 

•                     The TIRZ#1 Board approved a Chapter 380 Economic Development and Project Plan Implementation Agreement with McKinney Knittery/Downtown Dry Goods for Façade improvements consisting of storefront restoration on December 1, 2020.

 

•                     The agreement was amended in October of 2021 to extend to March 31, 2022.

 

FINANCIAL SUMMARY: 

 

•                     This amount falls within the $25,000 per qualifying project for Façade Improvements under the TIRZ project plan.

 

•                     These funds were originally approved in 2020-21 budget but not were not awarded. Under the TIRZ#1 policy plan, these funds carry over year to year.